DEL RIO, Texas — Val Verde County Commissioners Court has unanimously moved forward with a plan to finance approximately $2.175 million for county road projects, with funding to be distributed among the county’s four precincts based on the number of road miles each precinct maintains.

Commissioners voted 5-0 to authorize the financing plan and move forward with issuing tax notes for county projects.

County officials later clarified how the road funding would be divided.

Under the plan, each precinct would receive approximately $5,000 for every mile of county road listed in its road log.

Precincts 1 and 3 would receive an additional $1,000 per road mile because Precincts 2 and 4 received that additional amount during the previous fiscal year.

Officials said the money would therefore be divided among the four precincts based on their respective road mileage rather than being split evenly.

The meeting did not include a detailed list identifying which individual roads would receive improvements.

No Increase to Debt-Service Tax Rate Projected

During the financial presentation, PFM Financial Advisors told commissioners its analysis showed the additional $2.175 million could be financed without increasing the county’s Interest and Sinking, or I&S, tax rate.

The analysis considered existing county debt, property values and projected property-value growth.

The County has also already included an estimated payment for the financing in its 2026-2027 I&S budget.

Final Interest Rate Still Unknown

The County has not yet locked in an interest rate.

Financial advisers estimated that a roughly seven-year financing term could currently carry an interest rate between approximately 4.25% and 4.75%, but the actual rate will depend on competitive bank bids.

The financing opportunity is expected to be sent to more than 60 local, regional and national banks.

Bank bids are scheduled to be due October 20, with the results expected to return to Commissioners Court on October 21.

If commissioners accept the financing terms, the proposed closing date is November 19, when the funds could become available to the County.

Commissioners also chose to wait before beginning expenditures tied to the financing, saying they wanted to see the actual interest rate before committing the money.

Officials specifically discussed the risk of budgeting around rates in the 4.25% range only to see bids come back closer to 5%.

County Says Existing Debt Has Fallen

During the discussion, county officials said Val Verde County borrowed approximately $24.5 million between 2019 and 2023.

Officials said approximately $10 million of that debt had been paid down by the end of 2026, leaving roughly $14 million in principal outstanding.

The new $2.175 million financing would add additional debt, but county financial advisers said the current plan can be structured without raising the I&S tax rate.

The next major question will be how much money each precinct receives under the road-mileage formula — and which specific county roads commissioners ultimately choose to improve.

DRNN will continue tracking the financing when the bank bids return to Commissioners Court.